Any question, rule number, or answer reported as wrong will get looked at manually in a couple of days. Please write what is wrong with this flash card and what it should be which will speed up the correction process. -Thank you!
Front #89
ABTH 100.14
A train is stopped in a siding and has cut a road crossing to avoid blocking traffic. Three hours later, the crew recouples the train and is ready to depart. Which air brake test is required before departing? Select the best answer.
Answer: Air brake test when cutting off and recouplingFeedback: This test is only applicable if the time has not exceeded 24 hours. The brake pipe has not been compromised by cutting the road crossing. The train is being put back together the same way it was before being uncoupled.