Front #69

ABTH 105.5.1

A train check on a distributed power train may take up to two minutes to complete. While waiting for the results of the train check, the crew may start moving their train. However, the crew must receive a Pass result before the movement of the train exceeds the train's length and before train speed exceeds ________.


  1. Train must not begin moving before receiving a Pass.
  2. 20 mph
  3. 10 mph
  4. 5 mph
Back #69
Flag

ABTH 105.5.1


Answer: 10 mph
Feedback:
The train must not move further than one train length, unless the entire train is visually inspected or the changing brake pipe pressure readings from the DP remotes or ETD indicate that the brake pipe is not obstructed. Best practice is to wait for the result of a train check because a Fail would require stopping. There are conditions, such as being stopped at a crossing, that may require moving with the train check is initiating.