Front #68

ABTH 105.5.1

To initiate a train check, the engineer must make at least a ____ psi brake pipe reduction.


  1. 20
  2. 6-8
  3. 15
  4. 10
Back #68
Flag

ABTH 105.5.1


Answer: 10
Feedback:
The train check soft key will not appear on the screen without at least a 10 psi reduction.