Front #289

GCOR 18.2

When taking charge of a train in PTC territory, or before entering PTC territory, what must the engineer confirm before the train can depart? (Select all that apply.)


  1. The PTC circuit breakers and cut out switches are in the appropriate positions
  2. The GTB covers the route of the train.
  3. The PTC system is initialized on all locomotives in the head end consist
  4. The PTC system on the controlling locomotive is initialized
Back #289
Flag

GCOR 18.2


Answer: - The PTC circuit breakers and cut out switches are in the appropriate positions - The PTC system on the controlling locomotive is initialized - The GTB covers the route of the train.
Feedback:
Crews are responsible for verifying the PTC system is initialized with the correct GTB number and ensuring the limits listed on the GTB encompass the entire route.